Year 3 of the Seismic Upgrade & Mudslide Repair programme started in April 2019 and the construction teams worked through to mid-October, after which it is too cold for construction work.

This year saw refurbishment of the third residence, named Taklangla, out of the eight residential buildings to be done. The teams also completed the second of four new Eco-Shower buildings, plus the completion of the refurbishment of the two-storey Junior School building. The photos here are the Junior School building being completed and a ribbon-cutting ceremony when it was handed back to the school Principal for student use.

1 JSN    2 JSN   4 JSN

5 JSN   6 JSN   7 JSN